Major Project Milestones


  • Project Started in July 2016
  • CEQA EIR Finalized in July 2017
  • Request for Proposals to Design-Build teams issued in August 2017
  • Design-Builder Selected in December 2017
  • Groundbreaking Ceremony in September 2018
  • 100% SDs Tenant Improvement in October 2018
  • Foundations Started in October 2018
  • Foundations Completed in April 2019
  • First Piece of Steel Installed in April 2019
  • Topping Out in September 2019

3-Week Look-Ahead Schedule


·