8/06/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, August 7 - Material Deliveries (3:30pm-8:30pm)
  • Saturday, August 8 - Day Shift
  • Sunday, August 10 - Day Shift
  • Tuesday, August 11 - Furniture Delivery (5:00pm – 11:00pm)
  • Wednesday, August 12 - Material Delivery (2:00pm-6:00pm)
  • Thursday, August 13 - Material Deliveries (3:30pm-6:00pm)
  • Saturday, August 15 - Day Shift

4:00am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

07/29/20 SBE/DVBE Quarterly Update

Click images above for further details.


7/29/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Wednesday, July 29 - Material Deliveries (3:30pm-6:00pm)
  • Thursday, July 30 - Material Deliveries (3:30pm-6:00pm)
  • Friday, July 31 - Furniture Delivery (3:00pm-9:00pm)
  • Saturday, August 1 - Day Shift
  • Monday, August 3 - Furniture Delivery (3:00pm-9:00pm)
  • Tuesday, August 4 - Material Deliveries (3:30pm-6:00pm)
  • Wednesday, August 5 - Material Delivery (2:00pm-6:00pm)
  • Thursday, August 6 - Material Deliveries (3:30pm-6:00pm)
  • Friday, August 7 - Material Deliveries (3:30pm-8:30pm)
  • Saturday, August 8 - Day Shift

4:00am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

7/16/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, July 17 - Furniture Delivery (3:00pm-9:00pm)
  • Saturday, July 18 - Day Shift
  • Tuesday, July 21 - Material Delivery (3:00pm-9:00pm)
  • Wednesday, July 22 - Material Deliveries (3:30pm-6:00pm)
  • Thursday, July 23 - Material Deliveries (3:30pm-6:00pm)
  • Friday, July 24 - Furniture Delivery (3:00pm-9:00pm)

4:00am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

7/10/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, July 10 - Concrete Placement (5am Start)
  • Saturday, July 11 - Day Shift
  • Monday, July 13 - Furniture Delivery (3:00pm-9:00pm)
  • Tuesday, July 14 - Material Delivery (3:30pm-6:00pm)
  • Friday, July 17 - Furniture Delivery (3:00pm-9:00pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

7/01/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, July 2 - (3:30pm-6:00pm)
  • Wednesday, July 8 - (3:30pm-6:00pm)
  • Thursday, July 9 - Concrete Placement
  • Friday, July 10 - Concrete Placement

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

6/24/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, June 25 - (3:30pm-6:00pm)
  • Friday, June 26 - Concrete Placement (4am set-up, 5am Start)
  • Saturday, June 27 - (7:00am-7:00pm)
  • Sunday, June 28 - (7:00am-3:00pm)
  • Wednesday, July 1 - (3:30pm-6:00pm)
  • Thursday, July 2 - (3:30pm-6:00pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

6/18/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, June 19 - (3:30pm-6:00pm)
  • Saturday, June 20 - (7:00am-7:00pm)
  • Sunday, June 21 - (7:00am-3:00pm)
  • Tuesday, June 23 - (3:30pm-6:00pm)
  • Thursday, June 25 - (3:30pm-6:00pm)
  • Friday, June 26 - Concrete Placement (4am set-up, 5am Start)
  • Saturday, June 27 - Day Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

6/10/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, June 12 - Concrete Placement (3:30pm-7pm)
  • Saturday, June 13 - (7am-7pm)
  • Sunday, June 14 - Day Shift (7am-3pm)
  • Wednesday, June 17 - (3:30pm-6:00pm)
  • Friday, June 19 - (3:30pm-6:00pm)
  • Saturday, June 20 - Day Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

6/04/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, June 6 - Day Shift
  • Tuesday, June 9 - Swing Shift (3:30pm-6:00pm)
  • Wednesday, June 10 - Swing Shift (3:30pm-6:00pm)
  • Friday, June 12 - Concrete Placement (4:30am Start)
  • Saturday, June 13 - Day Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

5/27/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, May 30 - Day Shift
  • Tuesday, June 2 - Swing Shift (3:30pm-6:00pm)
  • Wednesday, June 3 - Swing Shift (3:30pm-6:00pm)
  • Tuesday, June 9 - Swing Shift (3:30pm-6:00pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

5/20/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, May 21 - Swing Shift (3:30pm-6:00pm)
  • Friday, May 22 - Concrete Placement (4:30am Start)
  • Tuesday, May 26 - Swing Shift (3:30pm-10:00pm)
  • Wednesday, May 27 - Swing Shift (3:00pm-10:00pm)
  • Saturday, May 30 - Day Shift
  • Tuesday, June 2 - Swing Shift (3:30pm-6:00pm)
  • Wednesday, June 3 - Swing Shift (3:30pm-6:00pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

5/14/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, May 16 - Day Shift
  • Tuesday, May 19 - Swing Shift (3:30pm-6:00pm)
  • Wednesday, May 20 - Swing Shift (3:30pm-6:00pm)
  • Thursday, May 21 - Swing Shift (3:30pm-6:00pm)
  • Friday, May 22 - Concrete Placement (4:30am Start)
  • Tuesday, May 26 - Swing Shift (3:30pm-10:00pm)
  • Wednesday, May 27 - Swing Shift (3:30pm-10:00pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.

5/06/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, May 9 - Day Shift (4:30am Start)
  • Tuesday, May 12 - Swing Shift (3:30pm-6:00pm)
  • Thursday, May 14 - Swing Shift (3:30pm-6:00pm)
  • Saturday, May 16 - Day Shift
  • Tuesday, May 19 - Swing Shift (3:30pm-6:00pm)
  • Wednesday, May 20 - Swing Shift (3:30pm-6:00pm)
  • Thursday, May 21 - Swing Shift (3:30pm-6:00pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


5/04/20 Road Closure

The following roads will be closed from 6:00pm to 6:00pm on Friday, May 15 - Saturday, May 16:

  • Road closure will be setup to remove the crane on 8th Street.

    8th Street will be closed from Q to O Streets to disassemble the crane. P Street will be closed at 9th Street to 7th Street.

    Click image above for further details.

Detours will be setup to direct traffic around road closures.


4/29/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday. April 30 - Swing Shift (3:30pm - 6pm)
  • Saturday, May 2 - Day Shift
  • Tuesday, May 5 - Swing Shift (3:30pm - 6pm)
  • Wednesday, May 6 - Swing Shift (3:30pm - 6pm)
  • Saturday, May 9 - Day Shift (4:30am Start)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


04/24/20 Neighborhood Outreach

Click images above for further details.


4/22/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, April 25 - Concrete Placement (6am) and Day Shift
  • Sunday, April 26 - Day Shift
  • Tuesday, April 28 - Swing Shift (3:30pm - 6pm)
  • Thursday. April 30 - Swing Shift (3:30pm - 6pm)
  • Saturday, May 2 - Day Shift
  • Tuesday, May 5 - Swing Shift (3:30pm - 6pm)
  • Wednesday, May 6 - Swing Shift (3:30pm - 6pm)

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


4/16/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, April 17 - SMUD Vault Work (10:30pm - 4am)
  • Saturday, April 18 - Day Shift
  • Monday, April 20 - Swing Shift
  • Wednesday, April 22 - Swing Shift
  • Saturday, April 25 - Day Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


4/09/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, April 10 - Swing Shift
  • Saturday, April 11 - Day Shift
  • Monday, April 13 - Swing Shift
  • Tuesday, April 14 - SMUD Vault Work (7:30pm - 4am)
  • Wednesday, April 15 - SMUD Vault Work (10:30pm - 4am)
  • Thursday, April 16 - SMUD Vault Work (24 hours)
  • Friday, April 17 - SMUD Vault Work (10:30pm - 4am)
  • Saturday, April 18 - Day Shift
  • Wednesday, April 22 - Swing Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


4/07/20 Off Hours Construction Work

NNRH will be performing night work starting 4/13 thru 4/17, and again 4/20 thru 4/25. In coordination with City and Regional Transit at the intersection of 7th and O street, starting on 4/14, 4/15, 4/17 & 4/18 from 10:30 PM through 3:30 AM, this work requires turning off power to the light rail system on O Street and is scheduled at night in order not to impact service. This work will have significant noise associated with driving piles to install a SMUD vault.

Turner Construction Company apologizes in advance for the inconvenience this may cause.

Thank you for your patience.


4/01/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, April 2 - Swing Shift
  • Friday, April 3 - Swing Shift
  • Saturday, April 4 - Day Shift
  • Monday, April 6 - 4:30am Concrete Placement
  • Tuesday, April 7 - Swing Shift
  • Wednesday, April 8 - Swing Shift
  • Thursday, April 9 - Swing Shift
  • Friday, April 10 - Swing Shift
  • Saturday, April 11 - Day Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


3/31/20 Road Closure

The following roads will be closed from 7:00pm to 6:00am on Tuesday, April 14 - Saturday, April 18:

  • Closure of 7th Street between N and P Streets

    7th Street will be closed to through traffic between N street and P Streets. Residents will be escorted through the lane closer by flagger if parking at Downtown Commons.

    Click image above for further details.

7th Street will be closed and detours will be setup directing traffic to 9th Street southbound.


3/27/20 Road Closure

The following roads will be closed from 7:00am to 5:30pm on Monday, April 13 - Wednesday, April 22:

  • Closure of 7th Street between N and P Streets

    Lane closure will be setup for construction within the intersection of 7th/ O street blocking the left hand through lane. Traffic will be required to merge to the right lane for through traffic.

    Click image above for further details.

7th Street will remain open to through traffic but may have limited congestion with a single lane open.


3/25/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, March 27 - Swing Shift
  • Saturday, March 28 - Day Shift
  • Sunday, March 29 - Day Shift
  • Wednesday, April 1 - Swing Shift
  • Saturday, April 4 - Day Shift
  • Wednesday, April 8 - Swing Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


03/24/20 Critical Infrastructure Workers

The California State Public Health Officer and Director of the California Department of Public Health is ordering all individuals living in the State of California to stay home or at their place of residence, except as needed to maintain continuity of operation of the federal critical infrastructure sectors. The New Natural Resources Project continues in accordance with the Executive Department State of California's Executive Order N-33-20.

Click images above for further details.


3/24/20 Road Closure

The following roads will be closed from 6:30am to 3:30pm on Monday, March 30 - Tuesday, April 14:

  • Closure of P Street between 7th and 8th Streets

    Lane closure will be setup to perform Curtainwall (Glazing) installation on the Southside of the New Natural Resources project.

    Click image above for further details.

P street will remain with 1 lane open during the day and 2 lanes open by 3:30pm for Peak congestion of outbound traffic.


3/24/20 Road Closure

The following lanes will be closed from 6:00pm to 6:00pm on Saturday, March 28 - Sunday, March 29:

  • Blocking roadway with trucks and crane to build in P Street and stage crane on P Street (between 7th and 8th) in current construction zone.
  • 8th Street between Q Street and O Street/ P Street between 9th Street and 7th Street

    Click image above for further details.

P Street & 8th Street will be closed to through traffic from O Street (south) to P Street and from 7th Street to 9th Street. RT Train will not be impacted, vehicles parked on streets or surface parking lot will be directed by flaggers to exit on 9th Street or Q Street.


3/18/20 Road Closure

The following lanes will be closed from 7:00am to 5:00pm on Sunday, March 22:

  • Closure of 7th Street between N and O Streets
  • Lane closure will be setup to perform video camera of storm and sewer line, 7th street will remain open with reduced lanes.

    Click image above for further details.

7th Street will remain open with reduced through lanes and may have some congestion a peak travel time southbound on 7th Street.


3/18/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, March 21 - Day Shift
  • Monday, March 23 - 5am Concrete Placement or
  • Tuesday, March 24 - 5am Concrete Placement
  • Wednesday, March 25 - 5am Concrete Placement
  • Friday, March 27 - Swing Shift
  • Saturday, March 28 - Day Shift

6:30am early start every working day for the foreseeable future. Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


3/12/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, March 12 - Swing Shift (Evening)
  • Saturday, March 14 - Day Shift
  • Sunday, March 15 - Day Shift
  • Monday, March 16 - 4am Concrete Placement or
  • Tuesday, March 17 - 4am Concrete Placement
  • Saturday, March 21 - Day Shift

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


3/04/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Wednesday, March 4 - Swing Shift (Evening)
  • Thursday, March 5 - Swing Shift (Evening)
  • Saturday, March 7 - Day Shift
  • Sunday, March 8 - Day Shift
  • Monday, March 9 - Swing Shift (Evening)
  • Tuesday, March 10 - Swing Shift (Evening)
  • Thursday, March 12 - Swing Shift (Evening)
  • Saturday, March 14 - Day Shift

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


2/26/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Wednesday, February 26 - Swing Shift (Evening)
  • Friday, February 28 - Swing Shift (Evening)
  • Saturday, February 29 - Day Shift
  • Sunday, March 1 - Day Shift
  • Wednesday, March 4 - Swing Shift (Evening)
  • Saturday, March 7 - Day Shift

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


02/19/20 Neighborhood Outreach Event


2/18/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, February 21 - 4am Concrete Placement
  • Saturday, February 22 - Day Shift
  • Sunday, February 23 - Day Shift
  • Monday, February 24 - Evening
  • Wednesday, February 26 - Swing Shift (Evening)
  • Friday, February 28 - Swing Shift (Evening)
  • Saturday, February 29 - Day Shift

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


2/7/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Tuesday, February 11 - Starting at 5am
  • Saturday February 15 - Day Shift
  • Friday, February 21 - 4am Concrete Placement
  • Monday, February 24 - Evening

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


1/30/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, February 1 - Day Shift
  • Tuesday, February 4 - 4am Concrete Placement
  • Wednesday, February 5 - 4am Concrete Placement
  • Thursday, February 6 - 4am Concrete Placement
  • Saturday, February 8 - Day Shift

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


1/29/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following date:

  • Saturday, February 1 - Day Shift

Thank you for your patience.


1/15/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, January 25 - Day Shift
  • Sunday, January 26 - Swing Shift (4am Start)

Thank you for your patience.


1/14/20 Road Closures

The following roads will be closed from 7:00am to 7:00pm on Saturday, January 18th:

  • Closure of 7th Street between N and P Streets

    Regional Transit will not be impacted. Vehicles parked in the parking garage or on surface streets will be directed by flaggers to exit on O or N Streets.

    Click image above for further details.

The closure of these streets is to provide crane access for the complexity of corner glazing units.


1/09/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, January 10 - 4am Concrete Placement
  • Saturday, January 11 - Day Shift

Thank you for your patience.


1/03/20 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, January 4 - Day Shift
  • Sunday, January 5 - Day Shift
  • Monday, January 6 - 4am Concrete Placement
  • Friday, January 10 - 4am Concrete Placement

Thank you for your patience.


12/13/19 Off Hours Construction Work

Early hours concrete work is planned for:

  • Tuesday, December 17 - 5am Concrete Placement
  • Thursday, December 19 - 5am Concrete Placement
  • Saturday, December 28 - Day Shift
  • Monday, January 6 - 4am Concrete Placement

Thank you for your patience.


12/03/19 Off Hours Construction Work

In order to mitigate weather impacts to the project due to the heavy rain forecast over the next few days and through the weekend, we will be running our hoist and working extended hours.

Our weather mitigation crew will start at 6 am Wednesday, December 3 and will be operating continuously through the weekend.

This is in addition to the work planned for:

  • Tuesday, December 10 - 5am Concrete Placement
  • Friday, December 13 - 3am Concrete Placement
  • Thursday, December 19 - 5am Concrete Placement

Thank you for your patience.


11/18/19 Neighborhood Outreach Event


11/13/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, November 15 - 3am Concrete Placement
  • Saturday, November 16 - 7am Concrete Placement
  • Tuesday, November 19 - 5am Concrete Placement
  • Friday, November 22 - 5am Concrete Placement
  • Saturday, November 23 - Day Shift
  • Tuesday, November 26 - 4am Concrete Placement
  • Tuesday, December 10 - 5am Concrete Placement
  • Friday, December 13 - 3am Concrete Placement
  • Thursday, December 19 - 5am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


11/06/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Monday, November 11 - 4am Concrete Placement
  • Wednesday, November 13 - 4am Concrete Placement
  • Thursday, November 14 - 4am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


10/23/19 Lane Closure

The following lanes will be closed from 7:00am to 2:30pm on Saturday October 26th:

  • Closure of 1 lane on P Street between 7th-8th Street
  • Closure of 1 lane on 7th between P Street and N Street

    Click image above for further details.

The closure of these lanes is to add stripping to the crosswalks at 7th and P Street interceptions.


10/18/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Tuesday, October 22 - 4am Concrete Placement
  • Thursday, October 24 - 4am Concrete Placement
  • Friday, October 25 - 4am Concrete Placement
  • Wednesday, October 30 - 4am Concrete Placement
  • Friday, November 1 - 4am Concrete Placement
  • Tuesday, November 5 - 2am Concrete Placement
  • Thursday, November 7 - 4am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


10/02/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, October 3 - 4am Concrete Placement
  • Saturday, October 5 - Day Shift
  • Tuesday, October 8 - 4am Concrete Placement
  • Thursday, October 10 - 4am Concrete Placement
  • Friday, October 11 - 5am Concrete Placement
  • Friday, October 11 - Swing Shift
  • Tuesday, October 15 - 4am Concrete Placement
  • Friday, October 18 - 4am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


9/25/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, September 28 - Day Shift
  • Tuesday, October 1 - 4am Concrete Placement
  • Thursday, October 3 - 4am Concrete Placement
  • Friday, October 11 - Swing Shift - Until 7:30pm

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


9/24/19 Retail Leasing Opportunities

For additional information, please contact Tony Psihopaidas at 916.375.4040 or Kari Chism at 916.375.4048.


9/19/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, September 19 - Swing Shift - Until 7:30pm
  • Friday, September 20 - Swing Shift - Until 7:30pm
  • Saturday, September 21 - 6:30am - 7:30pm
  • Monday, September 23 - Wednesday, September 25 - Swing Shift - Until 7:30pm
  • Thursday, September 26 - 4am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


9/12/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, September 14 - Day Shift
  • Sunday, September 15 - Day Shift
  • Monday, September 16 - 2:30pm - 10:00pm
  • Tuesday, September 17 - 5am Concrete Placement
  • Tuesday, September 17 - 2:30pm - 10:00pm
  • Tuesday, September 18 - 6am Steel Work
  • Friday, September 20 - 5am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


9/05/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Saturday, September 7
  • Monday, September 9 - 5am Concrete Placement
  • Tuesday, September 10 - 5am Concrete Placement
  • Wednesday, September 11 - 2:30pm - 10:00pm
  • Thursday, September 12 - 2am Concrete Placement
  • Thursday, September 12 - 2:30pm - 10:00pm
  • Friday, September 13 - 5am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


8/28/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Thursday, August 29 - Level 10 East - 2am Concrete Placement
  • Tuesday, September 3 - 2:30pm - 10:00pm
  • Thursday, September 5 - Level 11 West - 2am Concrete Placement
  • Monday, September 9 - Level 11 East - 2am Concrete Placement
  • Tuesday, September 10 - Level 12 West - 2am Concrete Placement
  • Thursday, September 12 - Level 12 East - 2am Concrete Placement
  • Thursday, September 12 - 2:30pm - 10:00pm

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


8/22/19 Off Hours Construction Work

Construction work is planned to be performed outside normal working hours on the following dates:

  • Friday, August 23 - 2:30pm - 10:00pm
  • Saturday, August 24
  • Monday, August 26 - Level 9 East - 2am Concrete Placement
  • Tuesday, August 27 - Level 10 West - 2am Concrete Placement
  • Tuesday, August 27 - 2:30pm - 10:00pm
  • Thursday, August 29 - Level 10 East - 2am Concrete Placement

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


8/16/19 Swing Shift Work (2pm - 10pm)

On August 21 - 23, 27, September 3 and 12, swing shift work during the hours of 2pm - 10pm will occur.

Activities may create some noise impacts, but is not expected to exceed city noise ordinance. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


8/06/19 Outreach Event

Turner Construction is hosting a final Outreach Event for the trade packages listed below relative to the New Natural Resources Headquarters Building Project in Downtown Sacramento. Project Engineers and Managers overseeing these packages will be present to meet you.

We are looking for DGS certified SB and DVBE firms to bid direct to Turner. All subcontractors must be pre-qualified to submit a proposal. THE DUE DATE FOR PRE-QUALIFICATION PACKAGES IS at Tuesday, August 27, 2019 close of business. ONLY PRE-QUALIFIED SUBCONTRACTORS PROPOSALS WILL BE ACCEPTED. Pre-qualification packages may be requested from Tiffany McAvoy.

The overall project has a 25% SBE and 3% DVBE requirement.

BIDS ARE DUE WEDNESDAY SEPTEMBER 5, 2019 AT 2:00PM

To register for the event: Click Here

Project Description and Schedule: Turner is procuring over the next few months the balance of all packages for the New Natural Resources Headquarters in downtown Sacramento. This is a $520 million design build project that is currently under construction with structural steel now being erected and approximately half way to the 21st floor. Please see below for all packages currently bidding. Project is scheduled to be complete 3rd quarter of 2021.

Questions During Bidding: Direct all questions during bidding to Turner Construction via email to Brandon Valdez. Deadline to submit RFIs is August 27, 2019 at 5:00pm.

Prevailing Wages: The Contractor agrees to comply with all provisions of California Labor Code Sections 1771, 1775, 1776, 1777.5, 1813, and 1815

DVBE and SBE Requirements: Full participation by each prime and sub-tier is required. Proposals that address DVBE and SBE participation will be given special consideration.

Project Labor Agreement: There is a Project Labor Agreement on this project. All bidders must agree to this agreement.

Community Workforce Agreement: All contractors are to ensure apprentices complete AT LEAST 20% of the total work hours. All contractors are to ensure that AT LEAST 25% of the apprentice hours are completed by Targeted Workers. Targeted Workers are those persons that are residents of California and are either Veterans, have a criminal record or other involvement with the criminal justice system, persons receiving public assistance, persons emancipated from the foster care system, or women interested in joining the trades.

Turner Construction is signatory to the Carpenters and Laborers Union.


8/06/19 Off Hours Construction Work

Starting at 2am concrete placement will occur on the following days:

  • Thursday, August 15 - Level 8 West
  • Monday, August 19 - Level 8 East
  • Thursday, August 22 - Level 1 West (1am concrete placement)
  • Friday, August 23 - Level 9 West
  • Monday, August 26 - Level 9 East
  • Tuesday, August 27 - Level 10 West
  • Thursday, August 29 - Level 10 East
  • Wednesday, September 4 - Level 11 West
  • Friday, September 6 - Level 11 East
  • Tuesday, September 10 - Level 12 West
  • Thursday, September 12 - Level 12 East

Steel erection work will occur starting at 6am on the following days:

  • August 8, 9, 21, 22, 26 - 28, & 30.

Saturday, August 10, SMUD conduit installation and coring work will occur.

Activities may create some noise impacts. Workers are mindful of the hour of the day and will work as quietly as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


7/30/19 Off Hours Construction Work

On August 2, 6, 8, 15, & 19, starting at 2am pump set-up for 3am concrete placement will occur. Activities will create some noise impacts. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


7/26/19 Off Hours Construction Work

On July 30, starting at 2am pump set-up for 3am concrete placement will occur. Activities will create some noise impacts. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


7/21/19 Avoid Heat Stress

To avoid potential heat stress, some staff will work earlier shifts (starting at 6am) during the next several weeks. Activities may create some noise impacts, but the staff will work as quielty as possible. "Noise blankets" remain installed to help reduce the noise.

Thank you for your patience.


7/17/19 Off Hours Construction Work

On July 18, 25, and 29, starting at 2am pump set-up for 3am concrete placement will occur. On Saturday, July 20, removal of the south west corner temporary column will occur. Activities will create some noise impacts. "Noise blankets" have been installed to help reduce the noise.

Thank you for your patience.


7/11/19 Neighborhood Outreach Event


7/11/19 Off Hours Construction Work

Welding work and crane reconfiguration will occur Saturday, July 13 and continue through Sunday, July 14. On July 16 and 18 at 3am, pump set-up for a 3am concrete placement will occur. Activities will create some noise impacts. "Noise blankets" have been installed to help reduce the noise.

Thank you for your patience.


6/26/19 Off Hours Construction Work

Steel and welding work will occur Saturday, June 29. Wednesday, July 3, starting at 2am pump set-up for 3am concrete placement will occur. Activities will create some noise impacts. "Noise blankets" have been installed to help reduce the noise.

Thank you for your patience.


6/19/19 Early Morning Construction Work

Concrete work will occur Monday, June 24 and Wednesday, June 26, starting at 2am. Activities will create some noise impacts during hours of operation. The State has installed "noise blankets" to help reduce the noise.

Thank you for your patience.


6/17/19 Early Morning Construction Work

Concrete work will occur Tuesday, June 18, starting at 4am. Activities will create some noise impacts during hours of operation. The State has installed "noise blankets" to help reduce the noise.


6/12/19 "After Hours" Construction Work

Concrete work will occur Thursday, June 13, starting at 2am and again on Friday, June 14, in the evening hours.


6/10/19 Road Closures

The following roads will be closed from 6:00pm to 11:59pm from Friday July 12th through July 14th:

  • Closure of P Street between 7th and 9th Street
  • Closure of 8th between Q Street and O Street

    Click image above for further details.

The closure of these streets is to add an additional 100 feet of boom to the crane to provide a longer reach for the high riser.


5/24/19 Road Closures

The following roads will be closed from 8:30am to 2:30pm from Tuesday May 28th through Sunday June 2nd:

  • P Street between 7th and 8th Streets (one lane only)
  • 7th Street between N and P Streets (right lane only)

    Click image above for further details.

Excavation activities will create some noise impacts during hours of operation, and dust control will be implemented.


5/14/19 Road Closures

The following roads will be closed from 7am-7pm on Saturday 18th and Sunday 19th May:

  • P Street between 7th and 8th streets
  • 7th Street between P and Q Streets

    Click image above for further details.


5/1/19 "After Hours" Construction Work

Concrete/grout work will be occurring daily until 10pm through Friday 17th May.


4/30/19 Neighborhood Outreach Event


4/20/19 Road Closures

The following roads will be closed from 7am to 7pm on Saturday 20th April:

  • P Street between 7th and 8th Streets (complete closure)
  • 7th Street between N and Q Streets (one lane open to traffic)


4/4/19 Night Work

Please be aware, we will be pouring concrete at 3am on Thursday morning and apologize for any disruption.


4/5/19 Road Closures

The following roads will be closed from 8pm on Friday 5th April until 5:30am on Sunday 7th:

  • P Street between 7th and 9th street
  • 8th Street between O and Q Street

    Click image above for further details.


3/29-31/19 "After Hours" Construction Work
  • Friday, March 29th: Concrete pour, starting at 3am
  • Saturday, March 30th: Construction work occurring from 6am-10pm
  • Sunday, March 31st: Construction work occurring from 7am-10pm

2/26/19 Road Closures for Crane Delivery and Activities
  • Weekend of April 5th-7th: We will be taking delivery and erection of our crane, so 8th Street will be closed between Q Street and O Street.
  • Ongoing: Steel deliveries on O Street (entering the site via 8th Street and exiting via 7th Street).
  • Weekend of July 26th-28th: The crane will be retooled - 8th Street will be closed once again between Q Street and O Street.
  • End of October: Steel erection complete.
  • November: Crane will be moving HVAC equipment to the roof.
  • January 2020:Crane will be leaving the site.

1/16/19 Lane and Intersection Closures

Starting today, expect lane and intersection closures on 7th Street and P Street around the site. Work will mainly occur on weekends for the next couple of months. Anticipate using alternate routes. We apologize for any inconvenience.


1/31/19 Outreach Event - Phase III - (trade packages)

Turner is hosting an Outreach Event for Phase III trade packages relative to the New Natural Resources HQ Building project in Downtown Sacramento.

We are especially interested in bidding directly to SB and DVBE DGS certified firms.
Project Engineers and Managers overseeing these packages will be present to meet you.

Click here to register

Trade Packages Estimated Value
Acoustic Ceilings $5.5M
Interior Drywall $10.7M
Flooring $6.9M
Misc Metals $1.4M
Ornamental Stairs $3.6M

ALL firms (especially SB/DVBE) interested in bidding this project should email Tiffany McAvoy to get prequalified.

The overall project has a 25% SBE and 3% DVBE requirement, and full participation by each prime and sub-tier is required.

Project Description - Design Build - 21 story 875,000 sf office building.

Project Schedule - Project is scheduled to be complete 3rd quarter of 2021.

Prevailing Wages - The Contractor agrees to comply with all provisions of California Labor Code Sections 1771, 1775, 1776, 1777.5, 1813, and 1815.

DVBE and SBE Requirements - DVBE requirements are 3% and SBE requirements are 25% for this project. Proposals that address DVBE and SBE participation will be given special consideration.

DGS Certification: Easy to apply and can certification can be completed in a relatively short period of time. Click for detailed instructions on how to register.

Project Labor Agreement - There is a Project Labor Agreement on this project. All bidders must agree to this agreement. Non-union subcontractors can bid on this project.

Community Workforce Agreement - Apprentices must complete at LEAST 20% of the total work hours. In addition, at LEAST 25% of the apprentice hours must be completed by Targeted Workers. Targeted Workers are residents of California and are classified as:

  • Veterans;
  • Persons with a criminal record or other involvement with the criminal justice system;
  • Persons receiving public assistance;
  • Persons emancipated from the foster care system;
  • Women interested in joining the trades.

Union Affiliation - Turner Construction is signatory to the Carpenters and Laborers Union.


11/27/18 Outreach Event - Phase III - (Core & Shell)

Turner is hosting an Outreach Event for Phase III trade packages relative to the Natural Resources HQ Building project in Downtown Sacramento.

Click here to register

Prime contractors to Turner construction need to be prequalified with Turner prior to 12/05/18 to be considered. If this time frame is too short, sub-tier contracting opportunities are available. ALL firms interested in participating on this project should attend this event.

The overall project has a 25% SBE and 3% DVBE requirement, and full participation by each prime and sub-tier is required.


11/01/18 Matchmaking Event (Formerly known as "Meet the Primes")

Turner Construction is hosting a Matchmaking Event (formerly known as "Meet the Primes") at their job site office:

750 N Street, Sacramento
Thursday, November 1, 2018, from 3:00 to 5:00 pm

Our primes are waiting to meet you. We welcome all sub tier subcontractors—even those not yet certified (we can work on certification afterwards).

We are looking for DGS certified SB or DVBE firms in these trades ONLY:

  • Shotcrete
  • Sawcutting
  • Excavation
  • Formwork
  • Lumber Supplier
  • Off-haul Spoils Trucking

If you wish to prequalify with Turner, please send an email to Debbie Devires at ddevires@tcco.com and she will guide you through the process.

We will host additional Matchmaking Events as necessary for other trade packages.

The Natural Resources Headquarters Building project has a 25% SB and 3% DVBE goal on this project.


10/29/18 "Meet the Primes" Event

Turner Construction is hosting a "Meet the Primes" Event on at their job site office:

750 N Street, Sacramento
October 29, 2018, from 4:00 to 6:00 pm

Our primes are waiting to meet you. We welcome all sub tier subcontractors—even those not yet certified (we can work on certification afterwards).

To register for the event: Meet the Primes Event - Natural Resources Headquarters Building Project

We are looking for DGS certified SB or DVBE firms in these trades ONLY:

  • Fire Stopping
  • Coring
  • Trucking
  • Insulators
  • Ready Mix Trucking

If you wish to prequalify with Turner, please send an email to Debbie Devires at ddevires@tcco.com and she will guide you through the process.

We will host additional Meet the Primes Event as necessary for additional trade packages.

The Natural Resources Headquarters Building project has a 25% SB and 3% DVBE goal on this project.


10/25/18 Community Outreach Event
Turner Construction will be holding community outreach event from 5 pm to 7 pm at 750 N Street in the Subterranean Building. All interested parties are welcome to attend.

9/20/18 Groundbreaking Ceremony
DGS will hold a groundbreaking ceremony (by invitation only) at the construction site.
A livecast of this event can be seen at 10 am on DGS's Facebook page or on our Instagram page.

7/31/18 Community Outreach Event
Turner Construction held a community outreach event: Event Presentation

3/19/18 Hochtief to Build $520M HQ for CA Department of Natural Resources
Turner Construction, a subsidiary of Germany's Hochtief, has won a design-and-build contract from the California Department of General Services to build a new headquarters in the state capital of Sacramento.
— Global Construction Review

New CA Government Building Expected to Achieve Net-zero Energy
As it moves closer to building a net-zero energy headquarters, California's Department of General Services recently selected a design-build partnership to plan and erect a 20-story office tower in Sacramento. — Proud Green Building